| PROJECT PORTFOLIO |
Standard Bank, Kimberley and Upington
 |
Project type: Shop fittings
Project value: R6 531 135.80
Duration: a total of 7 months
Status: completed
This was yet again a first of its kind for Afri-Devo as the company had not done shop fittings at this level before. The work involved partitioning, suspended ceilings, floor coverings, tiling, wall paper and forming curved bulk cades. For the main branch in Kimberley, fittings were done on three floors to the strict standard bank brand requirements and timelines as the branch was due for opening.
The project was delivered on time and to expected quality such that we were awarded the same kind of work at the Upington branch, which this time around was a live conversion with the bank fully operational as we worked. This branch was also completed satisfactorily in terms of delivery time and the quality of work.
|
|
|
| |
|